The Police National Computer went live in 1974, and it is still humming away on a Fujitsu mainframe in a datacentre in Hendon, north London.
I read The Register's latest report on the PNC and its missing support deal over a cheese sandwich at my desk, and my first reaction was a laugh. Twenty-six home secretaries have come and gone while it kept running. My second reaction was less cheerful, because I've stood in plenty of server rooms that tell a smaller version of the same story.
A quick recap, then.
The Home Office had planned to retire the PNC by this March, the point at which its support was due to run out, according to an accounting officer assessment The Register cites.
That deadline has gone. The department now says it aims to start decommissioning from next March. And a minister, Lord Hanson, recently told the House of Lords in a written answer that the old system may still be needed early in the year after that.
The replacement isn't exactly new either. Launched in 2016, the National Law Enforcement Data Service had a target finish of 2020 and a budget of £671m, then had to be delayed and reset. Parts of it are live now. The rest is still being built.
Why is a 1970s police system so hard to switch off?
A system like the PNC is hard to switch off because too much depends on it to risk even a short gap. The National Audit Office calls it the most important national policing information system in the UK, used by all 45 local police forces and 127 other organisations, and the NAO found it was searched or updated 133 million times in 2019-20 alone.
Nobody turns that off on a Friday and hopes for the best on Monday.
But there's a quieter reason too, and it's the one that keeps me interested. Back in 2021 the Public Accounts Committee found the team looking after the PNC was under-resourced, with several of its staff close to retirement. And the plan back then was to lean on in-house support once full manufacturer support for the database ended.
Put those two findings side by side and you get a slightly queasy feeling.
To be fair to the Home Office, a source close to the matter has since told The Register that a support agreement for the database software does exist. But the department wouldn't comment, and The Register has put in a Freedom of Information request. I'm not going to pretend I know more than they do.
Does your business have its own version of the PNC?
In my experience, most businesses trading for fifteen years or more have at least one system that only one person fully understands. It's often an ERP customised to within an inch of its life, or a bespoke stock system written by a contractor who retired to Portugal, or a database nobody dares touch. It works, it's paid for and it keeps the invoices going out, so nobody touches it.
I sat with an IT manager a few weeks back whose entire order book ran through one of these.
She called the engineer who understood it "the oracle", and she wasn't joking. He was 63. And he'd started mentioning his allotment a lot.
None of which is a dig at old technology. Mainframes have a reputation for reliability, and mostly they earn it. And plenty of legacy platforms will outlive the shiny things bought to replace them. The risk is in the people around them.
What happens when the one person who knows it leaves?
When the only person who understands a legacy system retires or resigns, the business doesn't lose the system straight away, but it does lose the ability to change it safely, fix it quickly or plan its replacement with any confidence. Jobs that used to take an afternoon start taking weeks, and every upgrade turns into a gamble.
We've written before about how talent gaps in IT can slow down your operations, and a missing expert on a creaking platform is about the sharpest version of that problem I see.
The PNC has already had a taste of how badly small changes can go. In 2021, a scripting error in code meant to delete records that were due for removal wiped out around 413,000 police records instead. But they were recovered in the end, thankfully.
Then there's the supplier market. When Fujitsu's support contract for the PNC was renewed in 2022, for £48m, no other company tendered, The Register reports. If a government department can't find alternatives, a mid-sized manufacturer in the Midlands with a thirty-year-old system will have even fewer.
And the clock doesn't stop, because the NAO reported that moving the PNC onto a new operating system could take three years, with the Home Office estimating a cost of at least £30m once code rewriting is included.
How do you plan a handover before it becomes urgent?
Plan a legacy handover by writing down who knows what, honestly, and how close each of those people is to leaving or retiring. Then hire the successor while the incumbent is still there, so the knowledge passes from person to person rather than from a panicked trawl through old emails. An overlap of six months is comfortable, and three is the least I'd want.
The hire itself is the hard part.
You don't want someone who only knows the old stack, because then you've just reset the clock by twenty years. And you don't want a pure modernist who calls the system rubbish in week one and loses the incumbent's goodwill by Friday lunchtime. I've watched that second one happen, and it took the client months to repair.
What you're after is someone curious about the old thing and fluent in the new one.
For most of the clients I work with, that means bringing in a senior engineer or solution architect who can sit beside the incumbent, document as they go and own the migration plan when it comes.
Hiring a senior infrastructure engineer into that seat is a different brief from a normal backfill. Say plainly in the advert that learning the old system comes first, or you'll attract people who skip that part. Most of them will, given the chance.
Should a legacy handover be contract or permanent?
Legacy handovers often work best with both a contract and a permanent hire. A contractor who already knows the platform can capture what's in the incumbent's head quickly, while a permanent hire gives you someone who'll still be around when the migration finally lands. If the PNC is anything to go by, that could be a while.
In my experience the people who still know these older systems well mostly work on contract now, and they know exactly what they're worth, so budget for that rather than being surprised by it.
Look after the incumbent as well. They're often the most valuable and least thanked person in the IT team, and a handover can feel a lot like being shown the door. Talk to them early and let them help choose their successor. And if they'd like to stay on part-time for a bit, it's usually money well spent.
Somewhere in Hendon, a mainframe that has outlasted 26 home secretaries is still doing its job while everyone works out who will switch it off. Your own oracle deserves a better plan than that, made while they're still at their desk.
If someone in your team has started mentioning the allotment, our IT recruitment specialists are happy to walk you through what finding a successor might involve.